More Overview
Project Overview

Wyangala Dam Safety Upgrade, NSW

  • Client: John Holland Group
  • Services: Construction of a new Span bridge crossing on trout farm road and raising of the dam gate.
  • Size: 180m
Close

Project Description.

Value: $1,500,000

Construction Period: 9 Months

Location: Wyangala, NSW, 2808

Construction activities include:
⦁ In-situ concrete works for bridge construction and spillway including Cantilevered Parapets using Pre-assembled traveller unit.
⦁ Prefabricated steel reinforcement and formwork for substructure and superstructure.
⦁ Prefabricated dam gate units.